  1. % !TeX root = proposal.tex
  2. \begin{landscape}
  3. \subsection{Project Schedule}
  4. \begin{table}[h!]
  5. \centering
  6. \begin{ganttchart}[
  7. y unit title=0.5cm,
  8. y unit chart=0.5cm,
  9. x unit=1.0mm,
  10. hgrid,
  11. today=2020-10-06,
  12. today label node/.append style={below=12pt},
  13. today label font=\itshape\color{blue},
  14. today rule/.style={draw=blue, ultra thick},
  15. title height=1,
  16. bar/.append style={fill=blue!50},
  17. bar incomplete/.append style={fill=gray!50},
  18. progress label text={$\displaystyle{#1\%}$},
  19. time slot format=isodate,
  20. milestone/.append style={inner sep=2pt, draw},
  21. title/.style={fill=heading!25, draw=black},
  22. link/.style={->, ultra thick, style=blue!50!black}
  23. ]{2020-10-05}{2021-04-30}
  24. \gantttitlecalendar{year, month=shortname} \\
  25. \gantttitle{40}{6}
  26. \gantttitlelist{41,...,52}{7}
  27. \gantttitlelist{1,...,16}{7}
  28. \gantttitle{}{6} \\
  29. \ganttbar[progress=50]{Literature Review}{2020-10-05}{2020-10-22}\\
  30. \ganttbar[progress=0]{Neural Network in software}{2020-10-12}{2020-11-11}\\
  31. \ganttbar[progress=0]{Channel Model Simulation}{2020-10-12}{2020-11-11}\\
  32. \ganttbar[progress=0]{FPGA Data structures}{2020-10-12}{2020-10-26}\\
  33. \ganttbar[progress=0]{FPGA ANN Implementation}{2020-10-26}{2020-11-25}\\
  34. \ganttbar[progress=0]{Training FPGA}{2020-11-25}{2020-12-18}\\
  35. \ganttlink[link/.append, link type=dr]{elem3}{elem4}
  36. \ganttlink[link/.append, link type=dr]{elem4}{elem5}
  37. \ganttmilestone{Project Proposal finalised}{2020-10-23}\\
  38. \ganttmilestone{Progress Report \#1}{2020-11-11}\\
  39. \ganttmilestone{Progress Report \#2}{2020-12-02}\\
  40. \ganttmilestone{December Interim Report}{2020-12-16}\\
  41. \ganttmilestone{Progress Report \#3}{2021-02-05}\\
  42. \ganttmilestone{Progress Report \#4}{2021-03-05}\\
  43. \ganttmilestone{Progress Report \#5}{2021-04-13}\\
  44. \ganttmilestone{Poster Presentation}{2021-04-17}\\
  45. \ganttmilestone{Final Report}{2021-04-30}
  46. \ganttvrule{Reading Week}{2020-11-09}
  47. \ganttvrule{}{2020-11-15}
  48. \ganttvrule[vrule label node/.append style={anchor=north west}]{Holidays}{2020-12-18}
  49. \ganttvrule{}{2021-01-11}
  50. \ganttvrule{Reading Week}{2021-02-15}
  51. \ganttvrule{}{2021-02-21}
  52. \end{ganttchart}
  53. \caption{Project schedule and deadlines in a Gantt chart}
  54. \label{table:time}